Saujana 7 Pedestal Crane Load Test
In September 2012, Saujana Marine Sdn Bhd required the new Crane onboard their work barge to be commissioned by Crane manufacturer and load tested at our yard seafront, witnessed by ABS Class Surveyor. We also fabricate and supply skids and rack for crew usage.
All other works were completed within 2 weeks during vessel stay in our yard.
Workscope includes :-
1) Arrange and supply all water bags / Weights and load cell for Crane Pedestal Load Testing.
2) Provided competent personnels to assist in Load Test.
3) Fabricated and supply new waste skids for vessel usage.
4) Fabricated and supply new gas cylinder racks for vessel usage.
|